Reactive Maintenance Is Burning Your Margin
A Thika packaging line called us after a gearbox seized at 2am. Cost: KES 2.1M in lost output, emergency air freight for a gear, and a missed supermarket delivery penalty. The root cause was a KES 3,200 bearing that a 30-minute vibration check would have caught 3 weeks earlier.
Reactive (fix after failure) costs 3–5× preventive in Kenyan plants we audit. Unplanned downtime averages KES 500k per hour on packaging and KES 1.2M on cement. Preventive is not a cost — it is margin protection.
What Preventive Actually Is
Not “grease and hope.” It is time- or usage-based work before failure:
It sits between run-to-failure and predictive (vibration, thermography, oil analysis). Most Kenyan plants should start preventive, then layer predictive on critical (A) assets.
The Business Case — Numbers from Kenyan Plants
We tracked 47 lines across manufacturing, mining, and milling:
ROI math: A line with 5% downtime (18 days/year) at KES 400k/day = KES 7.2M lost. A KES 85k/month contract (KES 1.02M/year) that cuts downtime to 3% (11 days) saves KES 2.8M — 2.7× return, before safety and life.
How to Build a Program in 30 Days
Week 1: Asset Registry & Criticality
List every asset. Rank A (line stops if it fails), B (slowdown), C (nuisance). Focus 80% of time on A. Example: For a maize mill, the hammer mill and sifter are A; the office AC is C.Week 2: Tasks & Intervals
Pull OEM manuals + failure history. For each A asset, define tasks:Week 3: Schedule in CMMS
We use a simple sheet or free CMMS (we set it up). Daily tick-boxes for operators, weekly for artisans, monthly for engineers. Each task has a photo guide — in Swahili where needed.Week 4: Start & Measure
Kick off with toolbox talk. Track 3 KPIs on a whiteboard:Layering Predictive (Month 2–3)
What It Looks Like at Dynatec
We don’t sell a binder and leave. For KES 85k/month per line (Thika, Ruiru, Nairobi metro):
Case: Kwale mining — 340t excavators availability 98.1% (was 91%) after 250h preventive + oil analysis. Breakdowns -40% in 90 days.
Common failure: Starting with C assets because they’re easy. Start with A — that’s where money is.
Next: Want the exact 30-day template (sheet + photo guides) we use? Download it via the OSHA checklist lead magnet at /blog/blog-workplace-safety, or book a free plant walk at /quote — we audit in 1 day and propose in 24h.