Planning & Controls
Baseline, S-curve, EVM.
- • MSP/Primavera
- • Risk register
- • Weekly SPI/CPI
Project Management • Kenya • NCA/EBK Licensed • From KES 150,000
End-to-end project management for industrial installations, upgrades and turnkey facility projects.
→ PM fee 8–12% of install or lump sum from KES 150k — baseline, EVM, EOT, O&M
Project slipping, budget drifting, no single owner?
→ We own planning, procurement, install and handover — you get one report, one invoice, one date.
Avg. reply 4.2h • 127 quotes last 30 days • No spam, just a proposal.

10+ yrs • 200+ installs • Insured • 2-yr warranty
Most Kenyan projects don’t fail on site — they fail on paper. No baseline, no critical path, no EVM, no laydown plan. Then the 5 vendors point at each other and you hold the penalty. In Thika we owned planning, procurement, install and handover for 2 lines — one report, one invoice, one date. -72% downtime, +18% throughput, 22 days total, audit file on day 23.
Dynatec PMO is not a Gantt print. It’s MSP/Primavera + risk register + weekly SPI/CPI + vendor prequal + expediting + kitting + daily toolbox + QA/QC + NDT + punch list + O&M. We do turnkey — concept to handover — for manufacturing, energy and mining. Fee 8–12% or lump sum, audit free.
You don’t need more meetings. You need one owner who knows that a missing M10 bolt can stop a 75kW motor and that a 3-day delay on spares is a 22-day backlog.
The overrun hides in the baseline you never set. Without a baseline, ‘on track’ means nothing — you discover -30% at month 2 when it’s too late. We baseline in MSP/Primavera: WBS 200 tasks, critical path (typically 35% of tasks), S-curve (planned vs actual), SPI/CPI weekly. At -5% (SPI 0.95), we crash (add crew) or fast-track (parallel). At -30%, you’re writing EOT letters. In Thika, SPI dipped to 0.92 at week 2 (spares late 3 days) — we expedited at 6am, recovered by week 3, finished day 22. Without EVM, that 3-day became 14-day.
Procurement is not ‘order’. It’s spec + prequal + expediting + kitting + laydown — or it’s ‘material on site’ that isn’t. A 75kW motor needs M10×40 8.8 bolts (not 8, not 6.8), DN100 PN16 gaskets (not PN10), and 95mm² cable (not 70mm² derated). We prequal vendors (KEBS, NCA, past 3 jobs), expedit weekly (photo of goods + packing list), kit per work front (conveyor kit: motor + gearbox + belt + bolts + gaskets in one cage), and laydown by sequence (line 1 first, not random). In Kwale, kitting cut install search time 40% — artisans installed, not hunted.
QA/QC is not a check-box — it’s NDT, punch list, and O&M that NCA signs. Welding 6G (WPS/PQR), MPI/DPI on 100% butt welds, hydro 1.5× with chart, alignment ±0.05mm, megger >100MΩ, thermography at load, and punch list that hits zero before handover. O&M is 87 pages (GA, single-line, data sheets, spares, PM tasks) + as-builts + training. At Thika, NCA audit 0 observations because the file was complete on day 23 — not ‘we’ll send later’. That’s the difference between turnkey and ‘almost done’.
You don’t need 5 foremen and a WhatsApp group where everyone is ‘almost there’. You need one PMO that owns planning, procurement, install, and handover — one report (SPI/CPI + photos), one invoice (fixed-price + EVM), one date (baseline), and one audit file. That’s Dynatec PMO — from concept to handover, 10+ years, 200+ installs, Ruiru to Kwale, and we stay for the warranty.
MSP/Primavera + S-curve + EVM (SPI/CPI) — you see -5% at week 2, not -30% at month 2, and we crash before it’s EOT
Expediting + kitting + laydown — no ‘material on site’ lie, 40% less search time, artisans install not hunt
Daily report + QA/QC + NDT + punch list zero — NCA 0 observations on day 23, not ‘we’ll send docs later’
O&M 87 pages + spares + training — handover is a file and a CMMS, not a handshake and a receipt
HSSE + LOTO + permits — zero LTI in 200+ mobilizations — your safety file stays clean, insurer happy
Fee 8–12% or lump sum (from KES 150k) — you pay for control, not chaos — audit free, baseline in 2 days
If your last project handed over a receipt, not an O&M, you didn’t buy a project — you bought a problem and a 3-month chase. Let us baseline your next one in 2 days — you’ll see slippage at -5%, not -30%, and you’ll hold one file on day 23.
How It Works — No Surprises
01
Scope + WBS (200 tasks), critical path (35% of duration), baseline (S-curve), risk register (10 risks × probability × impact × owner), EVM setup (BAC, PV, EV, AC). 2 days with you, MSP/Primavera file + PDF, frozen. Without baseline, progress is opinion.
02
Spec (motor 75kW M10×40 8.8, not guess), prequal (3 vendors, KEBS/NCA, past jobs), expediting (weekly photo + packing list + inspection), kitting (per work front cage), laydown (by sequence). No ‘bolt missing’ stops a motor.
03
Daily toolbox (15min, HSSE + task), QA/QC (6G weld + MPI/DPI + hydro + alignment ±0.05mm + megger + thermography), punch list (weekly, to zero), EVM (SPI/CPI weekly graph). You get one report — SPI 0.98, photos, next week plan.
04
O&M 87 pages (GA, single-line, data sheets, spares, PM 124 tasks), as-builts (red-line), spares kit (6-month, labelled), training (O&M walk + CMMS + toolbox), warranty (2-year workmanship) + dashboard (availability, MTBF). Day 23 audit file — not day 73 chase.
What We Do
Baseline, S-curve, EVM.
Spec, buy, expediting, kitting.
Daily toolbox, QA/QC, punch list.
Case Study
Challenge
Multi-trade install
Solution
Dynatec PMO
Result
On time + docs
| Factor | Dynatec | Freelance / Import | In-house |
|---|---|---|---|
| Owner | Single PMO | Many vendors | You |
| Report | Weekly + dashboard | Ad-hoc | Manual |
| Handover | O&M + spares | Receipt | — |
Pricing Guidance
PM fee 8–12% of install, or fixed lump sum after scope. Audit free.
Get Your Fixed PriceSite audit free within Nairobi metro for contracts >3 months.
Why You Called Us
These aren’t “occasional issues”. They’re the weekly cost you stopped counting. Each one has a KES value hidden in your bill, your stops log, or your audit file. We make it visible in the 1-day audit, then remove it.
No baseline, no critical path — ‘on track’ is opinion, -30% discovered at month 2 when EOT is your only letter
5 vendors pointing — mechanical blames electrical, electrical blames civil, you hold penalty and no spares
Cost overrun 15% — no EVM, no SPI/CPI, no forecast — KES 18M → KES 20.7M with no file to show
Procurement lie — ‘material on site’ is a packing list, not a kitted cage — M10 bolt missing stops 75kW motor 3 days
QA/QC theatre — no NDT, no alignment log, punch list 47 items at handover — NCA findings, insurer questions
Handover receipt — no O&M, no spares, no training, no CMMS — you bought a problem, not a project
Deep Dive — The Work Behind the Promise
WBS 200 tasks (level 3), durations, dependencies (FS/SS), resources (crew, crane), and critical path (CPM) — typically 35% of tasks. Baseline S-curve (PV) vs actual (EV) vs cost (AC) → SPI = EV/PV, CPI = EV/AC. SPI 0.95 at week 2 means 5% behind — we crash (add 2 fitters, KES 40k) or fast-track (overlap piping + electrical). Cost of crash KES 40k vs cost of 14-day delay KES 1.12M (8×). You choose early because you see early.
Risk register: 10 risks (spares late P0.6×I KES 800k, rain P0.4×I 3d, NCA delay P0.3×I 5d) with owner and mitigation (expedite, tent, pre-submit). Weekly SPI/CPI graph + photo report + lookahead (next 2 weeks). In Thika, EVM caught 3-day spares delay at 6am Tuesday; by 10am we’d rerouted Ruiru→Thika van. No EVM? You’d learn at Friday meeting. That’s the difference between 22 days and 34 days.
Spec is not ‘motor 75kW’ — it’s 75kW, 1480rpm, B3 foot, IP55, IE3, M10×40 8.8 bolts (4×), DN100 PN16 gasket, 95mm² XLPE/SWA cable (derated). Prequal: 3 vendors, KEBS cert, NCA, past 3 jobs (call them), sample (not catalogue). Expediting: weekly call + photo of goods + packing list + inspection at factory (not at site when wrong). Kitting: per work front cage (conveyor 1 kit: motor + gearbox + belt + bolts + gaskets + tools) — not pallets of mixed bolts.
Laydown: by sequence (line 1 first, laydown near line 1, not at gate 200m away). Search time 40% down at Kwale because artisan walks 10m to kit cage, not 200m to store + phone. Spare bolt logic: M10×40 × 20% extra + 2× per motor — because one missing bolt can stop a motor and 22-day backlog starts with ‘we’re waiting for bolts’.
Daily toolbox: 15min, HSSE (LOTO, sling, arc flash), task (2 lines today: align line 1, pull cable line 2), permit (hot work, height). QA/QC: 6G weld (WPS/PQR), MPI/DPI 100% butt, hydro 1.5× chart, alignment PRUFTECHNIK ±0.05mm, megger >100MΩ, thermography at load, punch list (47 → 0 in 3 weeks). No punch zero = no handover — we don’t leave with open items.
Handover is not a handshake — it’s O&M 87 pages (GA, single-line EBK-stamped, data sheets, spares 6-month, PM 124 tasks, warranties, NDT, tests), as-builts (red-line, CAD), training (O&M walk, CMMS, toolbox with register), and dashboard (availability, MTBF, SPI/CPI final). At Thika, NCA 0 observations day 23 because file was complete — previous contractor had 5 findings and 3-month chase. That’s turnkey.
What You Get at Handover — No “We’ll Send Later”
Baseline MSP/Primavera (WBS 200, critical path, S-curve, risk register, EVM) — 2 days, frozen + PDF
Spec + prequal (3 vendors) + expediting (weekly photo) + kitting (per front cage) + laydown plan
Daily toolbox (HSSE + permits) + QA/QC (6G+NDT+hydro+alignment+megger+thermography) + punch zero + weekly SPI/CPI report
O&M 87 pages + as-builts + spares kit (6-month) + CMMS 124 tasks + training register + warranty (2-year)
Weekly one-report (SPI/CPI + photos + lookahead + risk) + one invoice + one date — 4.2h avg reply
Audit free, baseline in 2 days, mobilize 72h after approval — fee 8–12% or lump sum from KES 150k
In Thika, that handover file passed NCA with zero observations. The previous contractor’s “handover” was a receipt and 5 audit findings. Which file do you want to hand your boss on day 23?
Where We Do It — From Ruiru to Kwale
2 lines, -72% downtime, +18% throughput, 0 audit findings — one PMO.
340t fleet, 250h service, consignment, 98.1% availability — turnkey maintenance PMO.
Power, PFC, genset, solar hybrid — 95% KEBS pass, EVM controlled.
Sites, warehouses, infrastructure — one date, one file, NCA compliant.
Also: Nairobi, Thika, Athi River, Nakuru, Mombasa, Kisumu, Eldoret, Nanyuki — 24h audit in Nairobi metro, 72h nationally. Spur Mall, Ruiru — Ruiru warehouse, 3 mobile teams.
The Maths — What It Saves, What It Returns
Fee 8–12% on KES 18M install = KES 1.44–2.16M. Overrun without PMO averages 15% = KES 2.7M (KEBS data, NCA filings). You save KES 0.54–1.26M before counting spares -22%, energy -6%, and avoided penalty (EOT KES 80k/day × 14 days = KES 1.12M). In Thika, 22 days vs 34 days without PMO = 12 days × KES 120k/day margin = KES 1.44M recovered — fee paid twice.
EOT letters cost more than paper — they cost client confidence. SPI 0.95 warning at week 2 (crash KES 40k) vs SPI 0.70 at month 2 (EOT + 14 days + KES 1.12M penalty + store rent + idle crew KES 600k) = 42×. One PMO that owns 5 vendors is not overhead — it’s insurance that your handover is a file on day 23, not a chase to day 73.
We audit free in Nairobi metro for contracts >3 months because the numbers sell themselves. You’ll see the KES value of the 7 stops you stopped counting — on paper, before you pay.
What They Say — After We Left
“Five vendors became one PMO. One report every Friday — SPI, photos, next week. Spare bolt missing? They had kitted it. 22 days, zero punch, NCA zero. Previous project was 5 files and 3 months chase.”
Project Director — Manufacturing — Thika, 2 Lines, 22 Days Turnkey
Baseline in 2 days or 50% off PM fee. SPI/CPI weekly or fee refund for that week. Punch zero at handover or we stay at our cost. Fee 8–12% or lump sum from KES 150k — audit free, fixed-price proposal in 24h, mobilize 72h after approval.
NCA Category 3 • EBK-licensed • EPRA Class A • KEBS • OSHA 2007 • Insured • 10+ years • 200+ installs • Avg reply 4.2h • 127 quotes last 30 days • Ruiru HQ, Spur Mall.
You’ll get photos, not a pitch — and a fixed price in 24h with spares, timeline, and warranty. No provisional sums. No “we’ll send docs later”.
FAQ
Answers that unblock your purchase order.
8–12% or lump sum.
Yes, from concept to handover.
Get a fixed-price, audit-backed proposal for project management — reply in 4.2h average.